BRIEF:
Design and install containment and work perimeter scaffold spanning from one building to adjacent building, to assemble and install cladding and glazing to “Link Bridge” structure 10 storeys above ground.

FEATURES:

  • Full containment around steel structure of link bridge.
  • Crane installation of spanning scaffold trusses from 4 Parramatta Square to 6-8 Parramatta Square
  • Allowance in the overall scaffold structure for relative movement in the building structures by ~100mm – rolling bearings incorporated.
  • Progressive dismantle as ‘Link Bridge’ was clad & glazed.