Built Core – 4 & 6-8 Parramatta Square – Link Bridge Installation Scaffold
BRIEF:
Design and install containment and work perimeter scaffold spanning from one building to adjacent building, to assemble and install cladding and glazing to “Link Bridge” structure 10 storeys above ground.
FEATURES:
- Full containment around steel structure of link bridge.
- Crane installation of spanning scaffold trusses from 4 Parramatta Square to 6-8 Parramatta Square
- Allowance in the overall scaffold structure for relative movement in the building structures by ~100mm – rolling bearings incorporated.
- Progressive dismantle as ‘Link Bridge’ was clad & glazed.
Share
Categories
Related items
VILLAGE QUAY, RHODES
Brief Design and install a monorail and swinging stage installation to provide rapid access over…
Shape ABC
BRIEF: Complete access package including a Large-scale overhead protection throughout the Atrium. Suspended scaffolding &…
Barangaroo
BARANGAROO TOWER 3 BRIEF: Design & Install a cantilevered catch & containment platform installation to…
Hawkesbury Rail Bridge – Containment – Work Decks
BRIEF: Design and install catch / work platforms below the up and down rail lines,…