Built Core – 4 & 6-8 Parramatta Square – Link Bridge Installation Scaffold
BRIEF:
Design and install containment and work perimeter scaffold spanning from one building to adjacent building, to assemble and install cladding and glazing to “Link Bridge” structure 10 storeys above ground.
FEATURES:
- Full containment around steel structure of link bridge.
- Crane installation of spanning scaffold trusses from 4 Parramatta Square to 6-8 Parramatta Square
- Allowance in the overall scaffold structure for relative movement in the building structures by ~100mm – rolling bearings incorporated.
- Progressive dismantle as ‘Link Bridge’ was clad & glazed.
Share
Categories
Related items
SALT PAN CREEK RAILWAY BRIDGE TRUSS REPLACEMENT
Brief Design & Install a suspended scaffold installation to the underside of the railway bridge…
BRIDGEPOINT, SPIT JUNCTION
Brief Design & Install a suspended scaffold installation to the underside of the pedestrian bridge…
SYDNEY CRICKET GROUND UPGRADE
Brief Design and Install BCC compliant stairway installation to provide temporary public stair access between…
CHATSWOOD TO EPPING RAIL LINK – EPPING RAILWAY STATION
Brief Design and install a suspended, multi-tiered roof perimeter scaffold to provide working platforms and…