BRIEF:
Design and install catch / work platforms below the up and down rail lines, and in the cess. Access for re-transforming and re-railing works during rail shutdowns.
FEATURES:
- Integrated scaffold platforms bearing to existing bridge steel members. Fall protection for workers on rail.
- Platforms installed and relocated from existing bridge maintenance gantry, coverage of entire bridge spans achievable for maximizing work productivity during limited time frame rail shutdowns.
- Installation of platforms could be undertaken during normal hours, in preparation for rail shutdowns. Management of waterways below achieved during day works.
Share
Categories
Related items
WIN STADIUM, WOLLONGONG
Brief Design and install a propping tower installation to support the 100 Tonne stadium roof…
PORT BOTANY REDEVELOPMENT PROJECT
Brief Design and install a stretcher stairs and walkway bridge to provide access over the…
Sydney Harbour Bridge – Main Span Cross Girder Painting
Brief Design & Install suspended encapsulation scaffold installations to facilitate preparation and painting of the…
BRIDGEPOINT, SPIT JUNCTION
Brief Design & Install a suspended scaffold installation to the underside of the pedestrian bridge…