Westmead Hospital – Core cladding repair – Winch driven scaffold
BRIEF:
Above were asked by their client to provide an efficient solution to replace cladding on the 2 upper levels of the building. Individual cladding pieces were 3.8m in height each – Scaffolding was the solution.
A winch driven suspended scaffold was designed and installed with a 450kg WLL. This approach removed the need to scaffold from the base of the building to the top which would have added more time into the program and façade penetration for scaffold ties at each finished floor.
FEATURES:
- Scaffold was erected on ground floor then driven up into position in 3 sections
Share
Categories
Related items
WIN STADIUM, WOLLONGONG
Brief Design and install a propping tower installation to support the 100 Tonne stadium roof…
Sydney Harbour Bridge – Main Span Cross Girder Painting
Brief Design & Install suspended encapsulation scaffold installations to facilitate preparation and painting of the…
VILLAGE QUAY, RHODES
Brief Design and install a monorail and swinging stage installation to provide rapid access over…