BARANGAROO TOWER 1
Brief
Design and install a falsework solution to allow pouring of crane penetration infills at 3 levels, simultaneously. All penetrations directly above each other. Falsework needed to span over the penetration below, while allowing formwork installation to pour the slab above.
Features
- Falsework structures were built away from edge of penetration and rolled into position
- Access was maintained to pour the L03, L02 and L01 infills without obstruction due to falsework spanning over the voids
- U head jacks and internal ladder access allowed traditional formwork to be insalled quickly and safely
Project Name
BARANGAROO TOWER 1
Principal
Lend Lease
Installation
FalseworkK Scaffolds
Related items
CHATSWOOD TO EPPING RAIL LINK – EPPING RAILWAY STATION
Brief Design and install a suspended, multi-tiered roof perimeter scaffold to provide working platforms and…
Barangaroo
BARANGAROO TOWER 3 BRIEF: Design & Install a cantilevered catch & containment platform installation to…
BARANGAROO TOWER 1
Brief Design and install a custom cantilevered loading platform to install 3 sections of a…
Built Core – 4 & 6-8 Parramatta Square – Link Bridge Installation Scaffold
BRIEF: Design and install containment and work perimeter scaffold spanning from one building to adjacent…