BARANGAROO TOWER 3
BRIEF:
Design & Install a cantilevered catch & containment platform installation to be relocated progressively up the tower, providing overhead protection to enable facade pop-outs to be installed without interruption to groundworks below. The design and methodology to allow the scaffold to be launched, retracted and relocated in the shortest possible time to support program continuity.
FEATURES:
- Cantilevered Catch Platform Area – 5m x 33m with 5kPa load rating
- Tracks fixed to slab to guide travel on 30kN profiled steel wheels.
- Platform assembled from mobile trusses craned between levels via the loading platforms.
- Time to launch or retract the platform was 1 hour approximately.
Share
Project Name
Barangaroo
Principal
Lend Lease
Installation
Roll In / Roll Out Cantilevered Catch Platform
Related items
NORTHCONNEX TUNNEL – WILSON SHAFT
Brief Design & Install a suspended access stairs which can be progressively extended down the…
SYDNEY HARBOUR BRIDGE REFURBISHMENT
Brief Design and install a suspended scaffold installation to the underside of the Sydney Harbour…
Shape ABC
BRIEF: Complete access package including a Large-scale overhead protection throughout the Atrium. Suspended scaffolding &…
BARANGAROO TOWER 1
Brief Design and install a falsework solution to allow pouring of crane penetration infills at…