Brief
Design and install a falsework solution to allow pouring of crane penetration infills at 3 levels, simultaneously. All penetrations directly above each other. Falsework needed to span over the penetration below, while allowing formwork installation to pour the slab above.
Features
- Falsework structures were built away from edge of penetration and rolled into position
- Access was maintained to pour the L03, L02 and L01 infills without obstruction due to falsework spanning over the voids
- U head jacks and internal ladder access allowed traditional formwork to be insalled quickly and safely
Project Name
BARANGAROO TOWER 1
Principal
Lend Lease
Installation
FalseworkK Scaffolds
Related items
NORTHCONNEX TUNNEL – WILSON SHAFT
Brief Design & Install a suspended access stairs which can be progressively extended down the…
CENTRAL PARK – SKYDECK
Brief Design and install a large area work platform installation to be suspended from the…
Macquarie University Hospital – Swinging Stages- Clading Replacement
BRIEF: Swinging Stagesfor Cladding replacement FEATURES: Swinging Stages projecting through plant room rooves x 9…