BRIDGEPOINT, SPIT JUNCTION

Brief
Design & Install a suspended scaffold installation to the underside of the pedestrian bridge over Military Road, Spit Junction, to facilitate demolition of the existing bridge superstructure and construction of a new modern superstructure with billboards. The design and installation methodology to minimise traffic disruption and permit all demolition and construction works to proceed over the live traffic without restrictions.

Fatures

  • Preassembled 12m long trusses (9) delivered on semi-trailer and craned into position.
  • Containment Deck Area -28m x 12m
  • three upper working levels along both sides
  • Ties designed to permit unimpeded construction of the new bridge structure
  • Double skin containment system with printed façade replication
Project Name
Bridgepoint, SPIT JUNCTION
Principal
LIPMAN
Installation
Suspended Underbridge Access and Containment Scaffold