CENTRAL PARK – SKYDECK
Brief
Design and install a large area work platform installation to be suspended from the cantilevered Heliostat structure, some 100m above ground, to facilitate installation of sofit superstructure and cladding. Installation and dismantle methodologies to minimise risks associated with working at height.
Scaffold installation to be designed for 1 in 100 year wind event.
Features
- Skydeck Area – 15m x 5m
- Skydeck assembled at ground level and then raised up to position using scaffold hoists.
- Skydeck secured in working position with suspension chains.
- Access onto skydek from skygarden above.
Share
Project Name
Central Park - Skydeck
Principal
WATPAC
Installation
Suspended Traveling 'SKYDECK'
Related items
SYDNEY HARBOUR BRIDGE REFURBISHMENT
Brief Design and install a suspended scaffold installation to the underside of the Sydney Harbour…
Macquarie University Hospital – Swinging Stages- Clading Replacement
BRIEF: Swinging Stagesfor Cladding replacement FEATURES: Swinging Stages projecting through plant room rooves x 9…
VILLAGE QUAY, RHODES
Brief Design and install a monorail and swinging stage installation to provide rapid access over…
Shape ABC
BRIEF: Complete access package including a Large-scale overhead protection throughout the Atrium. Suspended scaffolding &…