PORT BOTANY REDEVELOPMENT PROJECT

Brief
Design and install a stretcher stairs and walkway bridge to provide access over the rail corridor between the work site and the site compound. The design to ensure the installation does not encroach into the rail corridor. The installation methodology to minimise track possession duration.

Features

  • 14.5m clear span bridge suspended between stretcher stair tower abutments.
  • Bridge pre-assembled then craned into position and connected to stair towers.
  • 1.4m wide bridge and stairways.
  • Stair towers anchored to concrete barriers for stability and wind resistance.
  • 2.5kPa load rating.
Project Name
Port Botany Redevelopment Project
Principal
Fulton Hogan
Installation
Access Bridge With Stairs