Sydney Harbour Bridge – Main Span Cross Girder Painting
Brief
Design & Install suspended encapsulation scaffold installations to facilitate preparation and painting of the main span cross girders. The design and methodology to ensure no obstruction to the travel of the main span gantry, and to allow the scaffolds to be readily relocated from cross girder to cross girder.
Features
- Each scaffold is 50m long x 7m wide x 3m high
- 84 suspension chain assemblies per scaffold
- Access onto scaffolds from bridge catwalks
Project Name
Sydney Harbour Bridge - Main Span Cross Girder Painting
Principal
RMS
Installation
Suspended Underdeck Access and Containment Scaffolds
Related items
Built Core – 4 & 6-8 Parramatta Square – Link Bridge Installation Scaffold
BRIEF: Design and install containment and work perimeter scaffold spanning from one building to adjacent…
BARANGAROO TOWER 1
Brief Design and install a custom cantilevered loading platform to install 3 sections of a…
Shape ABC
BRIEF: Complete access package including a Large-scale overhead protection throughout the Atrium. Suspended scaffolding &…
SYDNEY CRICKET GROUND UPGRADE
Brief Design and Install BCC compliant stairway installation to provide temporary public stair access between…